A Penhallow company - serving North Miami, FL
A remodeled kitchen with a wood island, painted cabinets and a plaster range hood

How Long Does Kitchen Remodeling Take? Timelines and What to Expect

Free Estimate on SiteCalls Answered by a Live Person, 24/7Background-Checked TechniciansA Local Team in North Miami

Last updated November 17, 2026

New painted shaker cabinets with an organized deep drawer
A small remodeled galley kitchen with cabinets to the ceiling
A walk-in pantry with wood shelving
A remodeled kitchen with a waterfall island and wood cabinets
An open kitchen and dining area after a remodel
A remodeled primary bathroom with a soaking tub and walk-in shower
A remodeled living room with built-in shelves around the fireplace
A single-story rear room addition with tall windows and a new patio
Every visit starts with

Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled

We have financing partners for your dream remodel*On approved credit; ask us about your options
Get your free estimate

How Long Does Kitchen Remodeling Take? Timelines and What to Expect

Custom cabinets ordered the same week demo starts add four to six weeks to nearly every kitchen remodel, yet most homeowners don’t hear this until after they’ve been eating takeout for a month. The timeline on your kitchen is mostly written before a single cabinet comes down: appliance lead times, cabinet production schedules, and permit wait times all get set in motion weeks earlier. In North Miami, where Miami-Dade permitting runs on its own clock and stone countertops go through a templating step most people have never heard of, understanding that sequence is the difference between a kitchen finished on schedule and one stuck waiting on a slab.

Call (888) 255-7411

This guide maps the full sequence for North Miami homeowners, phase by phase, with realistic day counts.

Quick Answer

A cabinet refresh takes 1 to 2 weeks. A full gut remodel that keeps the existing layout takes 4 to 6 weeks of construction, and a remodel that moves walls, plumbing, or electrical takes 6 to 10 weeks. Add design time and cabinet production lead time before demo ever begins, plus roughly 10 to 14 days for countertop templating and fabrication. From first decision to final walkthrough, most North Miami kitchen remodels run 10 to 16 weeks end to end.

Explore

Styles & brands we work with

  • Kitchen remodeling
  • Bathroom remodeling
  • Home additions & ADU
  • Roofing
  • Windows & doors
  • Driveway & pavers
  • Fence

Table of Contents

The Kitchen Remodel Sequence: What Happens Before Demo

The most useful thing to understand about kitchen timelines is that the clock on cabinet production and appliance delivery starts the day you sign off on the design, not the day demo starts. Everything else in the job bends around those two items. A kitchen with a 5-week cabinet lead time and a 6-week range delivery date has its critical path already set, and the construction phase simply has to fit the window between when the old kitchen comes out and when the new one arrives.

Here is the sequence, in order, with the triggers that start each clock:

  1. Design finalization. Layout locked, cabinet line and door style selected, door and drawer pull-outs specified, appliance models chosen by model number. This step drives everything, because cabinet lead times can’t be quoted until the line is chosen.
  2. Cabinet order and appliance order. Both go out the same week. Cabinet production typically runs 3 to 6 weeks depending on the line; appliance delivery depends on model and current allocation.
  3. Permit submission. Filed as soon as design is final. In Miami-Dade, this can run parallel with cabinet production.
  4. Demo. Scheduled to land so that the kitchen is ready to receive cabinets when they arrive, not weeks before.
  5. Rough-in and inspection. Plumbing and electrical moves get inspected before walls close.
  6. Cabinet install. The kitchen is now on the cabinet installer’s clock.
  7. Countertop template and fabrication. Stone counters cannot be templated until cabinets are fully set and shimmed level.
  8. Finish work. Backsplash, paint, trim, hardware, faucet, final inspection, punch list.

The North Miami part of this matters. A licensed general contractor in North Miami coordinates the inspection calendar with Miami-Dade so rough-in doesn’t sit waiting for a morning slot while cabinets are on the front porch. Our team has up to 22 years of experience with exactly this coordination, and it’s the reason our kitchen schedules don’t get pushed by a week for a routine inspection.

The Full Timeline, Phase by Phase

Here are realistic day counts for a North Miami kitchen remodel with the existing layout staying put. If you’re planning a larger project, our Kitchen Remodeling in North Miami page shows how the pieces fit together.

  • Design finalization: 1 to 3 weeks. Faster if you walk in with cabinet line and appliance models already chosen. Slower if you’re choosing between KraftMaid and Wellborn door styles across three visits.
  • Cabinet production: 3 to 6 weeks. Stock lines run shorter; semi-custom runs longer. KraftMaid and Wellborn both quote lead times by door style, so this number changes with the design, not with the season.
  • Appliance lead time: 2 to 10 weeks. The widest variable in the whole job. A common gas range may arrive in days; a specific panel-ready refrigerator or a range with a particular finish can take far longer. Choose models early, order by model number, and confirm the delivery date before demo is scheduled.
  • Permit submission and approval: 2 to 6 weeks. See the permit section below for the details.
  • Demo: 2 to 4 days. Removing cabinets, counters, appliances, and flooring. A dumpster gets set, and the crew strips to the studs where needed.
  • Rough-in and inspection: 3 to 7 days. Plumbing and electrical moves, plus any framing changes. The inspection has to happen before drywall closes.
  • Drywall, paint, and flooring: 1 to 2 weeks. Floors go in after paint, before cabinets, on most North Miami jobs.
  • Cabinet install: 2 to 4 days. Cabinets set, shimmed level, secured. Appliance installs follow the cabinets.
  • Countertop template and fabrication: 10 to 14 days. This is the step that routinely surprises homeowners. See the next section.
  • Backsplash, finish work, and final inspection: 1 to 2 weeks. Tile set, grout cured, faucet and hardware in, punch list walked.

The total: 10 to 16 weeks from design start to final walkthrough, with the largest single block of that being cabinet and countertop lead times, not labor.

Countertop Templating: The Step Nobody Warns You About

Countertop templating is the physical measurement of your installed cabinets that precedes cutting stone. It adds 10 to 14 days to every quartz, granite, or marble kitchen, and it’s the step that eats the most schedules when homeowners haven’t been told about it.

Here’s why it works this way. Stone countertops are cut to a template of your actual installed cabinetry, not to a drawing, because cabinets are never perfectly parallel and walls are never perfectly square. If cabinets have been set and shimmed level and the template is taken from the drawing instead, the slab can come back 1/8 inch off at a corner and there’s no fixing it without recutting. So the template visit has to happen after cabinets are set and level, with the sink and cooktop on site so cutouts can be mapped accurately. That means:

  • The template can’t be taken until cabinets are fully installed and shimmed. No exceptions.
  • The slab you selected has to be on hold or in stock, because Cambria, Silestone, and Caesarstone slabs are cut from the specific bundle you reserve.
  • Fabrication itself runs 5 to 10 days after template, depending on edge profile and fabricator backlog.
  • Installation is a half-day, then a 24-hour cure before the sink is connected.

So the sequence a homeowner should plan around is: cabinets installed, template visit, 10 to 14 days fabricating, then counter installation. If you’ve selected a Caesarstone slab that’s a special order, add the slab’s own delivery time to that window. A contractor who tells you countertops will be in “a few days after cabinets” hasn’t done a stone job recently.

Miami-Dade Permits: The Honest Wait Times

Miami-Dade County permits for a kitchen remodel currently run 2 to 6 weeks from submission to approval, and that window is set by the county’s review queue and by how complete the submission is. An incomplete application gets sent back for a correction cycle, and each correction adds time. The most common kick-backs we see are missing product approval numbers for impact-rated windows if the scope touches an exterior wall, missing electrical load calculations if the range is switching from gas to electric, and missing a site plan that doesn’t match what the existing drawings show.

What can and can’t be done while you wait for the permit matters too. You can order cabinets and appliances, finalize finish selections, and complete any demo that doesn’t require a permit (pulling base cabinets and appliances is typically allowed; touching plumbing or electrical lines is not, and not on a permit-driven project). What you cannot do is start plumbing or electrical rough-in before the permit is issued. Doing it ahead of time is the single fastest way to have an inspector red-tag the job and require the work to be opened back up.

The good news is that a permit wait can often run parallel to cabinet production. If your cabinet line quotes 6 weeks and your permit runs 4, the two clocks are already running at the same time and the permit doesn’t add to the schedule at all, provided the design was final before either clock started. That’s the coordination an experienced North Miami general contractor does before demo ever gets discussed, and it’s why our written schedule shows the permit number and its dates right alongside the cabinet order.

If your kitchen project grows into other rooms, our General Contractor in North Miami page covers how we sequence whole-home work, and the same permit-first discipline applies to any Bathroom Remodeling in North Miami project.

Three Timelines: Refresh, Full Gut, Layout Change

Not every kitchen project is the same scope, and the timeline changes more with the scope than with the square footage. Here are the three common cases with the specific variables that move each number.

1. Cabinet refresh: 1 to 2 weeks of construction

A cabinet refresh means keeping the layout and the counters, and replacing or refacing doors, drawer fronts, and hardware. Construction time is short because nothing structural moves and most jobs don’t require a permit. Variables that push it longer: cabinet door lead times (3 to 4 weeks even for a stock line, which usually dominates the timeline), and whether any plumbing or electrical is affected (if the sink stays in place, usually not).

2. Full gut, existing layout: 4 to 6 weeks of construction

Full gut with the layout intact means cabinets, counters, backsplash, floor, and appliances all come out and go back in, but walls, plumbing lines, and electrical circuits stay where they were. Construction runs 4 to 6 weeks because the permit still has to be pulled (kitchen cabinets, counters, and any appliance change usually triggers a permit in Miami-Dade), the rough-in inspection still has to clear, and every trade still has a place in the schedule. Variables that push it longer: countertop templating (10 to 14 days), an out-of-stock appliance model, or any unexpected condition behind drywall (old galvanized drains, ungrounded wiring from a prior remodel).

3. Layout change: 6 to 10 weeks of construction

A layout change means the work moves a wall, relocates the sink or the range, or combines the kitchen with an adjacent space. That’s where the timeline grows the most, because every relocated line triggers engineering, a plumbing or electrical permit amendment, and an additional inspection cycle. Variables that push it longer: structural changes (moving a load-bearing wall), window or door relocation (impact-rated products require product approvals, and James Hardie siding or a Therma-Tru door change triggers a separate inspection), and any change to the gas line (requires a licensed plumber and an additional inspection).

Across all three, the North Miami-specific factor that shows up most often is window and door replacement in the scope. Impact-rated product approvals are a frequent permit kick-back in Miami-Dade, and they can add 2 to 3 weeks to a layout-change job that a contractor hasn’t planned for.

What a Written Schedule Looks Like vs. a Verbal Promise

A written project schedule protects both homeowner and contractor: the homeowner knows what’s happening on which dates and when the kitchen will be usable, and the contractor has a documented sequence to work against. A verbal promise (“we should be done in a month”) protects neither, because when the schedule slips there’s no agreement to point to and no way to tell whether the slip was preventable.

A real written schedule, on a kitchen remodel in North Miami, should include:

  • Cabinet order date and confirmed production lead time in days. Not “a few weeks,” a number and an order confirmation number.
  • Appliance models and confirmed delivery dates. By model number, on the schedule, with the delivery address.
  • Permit number, submission date, and projected approval date. With a plan for what happens if the county requests corrections.
  • Demo dates and a defined arrival window (for example, “crew arrives between 8:00 and 9:00 a.m.”), not “sometime that week.”
  • Rough-in inspection date and the cabinet install date that follows. The gap between them should be zero dead time, not two weeks of waiting.
  • Template visit date and counter installation date. Both should be on the schedule on day one, because both are knowable once the cabinet install date is set.
  • Final walkthrough and punch list date. The point at which the kitchen is turned back over.

A written schedule with real dates is also where the guarantee lives. The Kingswell Guarantee operates on the same principle: say the price before the work, show up in the window we gave, leave the place cleaner than we found it, and put the guarantee in writing. Our written price before any work starts, and our 365-Day Done Right Promise on every project, are the same discipline applied to the schedule.

If you’d like to see how this plays out on our North Miami home page, the Penhallow Remodeling North Miami home walks through our process in more detail.

Before & after

See the difference

Before - Recent ProjectBeforeAfter - Recent ProjectAfter
Recent Project
Before - Full RestorationBeforeAfter - Full RestorationAfter
Full Restoration
Before - Complete UpgradeBeforeAfter - Complete UpgradeAfter
Complete Upgrade

Common Mistakes to Avoid

  • Ordering cabinets after demo. The single most common cause of a 4-to-6-week delay. Order cabinets the week the design is signed; schedule demo for the delivery window.
  • Choosing appliances by look instead of availability. A panel-ready refrigerator with a specific finish can take 8 to 10 weeks, and a kitchen can’t close without it. Check delivery dates with the model number before you commit.
  • Starting demo before the permit is issued. In Miami-Dade, this routinely gets a job red-tagged and costs more than waiting. Pull the permit, then demo.
  • Templating before cabinets are shimmed level. Stone cut to a template taken on an unlevel cabinet run will not sit right, and recutting adds weeks and dollars. Cabinets level, then template.
  • Moving the gas line as an afterthought. Gas line relocation requires a licensed plumber and a separate inspection, and it needs to be on the schedule before demo, not discovered mid-job.
  • Choosing a countertop material before checking slab availability. Cambria, Silestone, and Caesarstone slabs are cut from the specific bundle you reserve, and an out-of-stock color can add 3 to 4 weeks.
  • Accepting a verbal “done in a month.” Ask for the schedule in writing, with dates, before you sign anything.

When to Call a Professional

Call a general contractor when the kitchen scope touches plumbing, electrical, gas, or a load-bearing wall. Those elements require a licensed trade, a permit, and an inspection, and no amount of homeowner research can substitute for that. Call one earlier than you think you need to: the design finalization step (1 to 3 weeks) and the cabinet production step (3 to 6 weeks) can overlap with the permit wait (2 to 6 weeks), and coordinating those three clocks is what keeps the total at 10 to 16 weeks instead of 20 or more. A homeowner who calls a professional after demo has already started has already lost weeks.

Penhallow Remodeling North Miami offers free estimates in North Miami with a written price before any work starts. Call (888) 255-7411 to schedule yours. A live person answers 24/7.

Frequently Asked Questions

The Bottom Line

Installers leveling a new base cabinet during a kitchen remodel

Your kitchen timeline is set before demo starts. Finalize the design, choose cabinet models and appliance models by number, order both the week the design is signed, submit the permit the same week, and schedule demo for the cabinet delivery window. Then build in the two steps most homeowners don’t know about: the 10-to-14-day countertop templating window, and the permit review queue that runs parallel to cabinet production. A 10-to-16-week North Miami kitchen is achievable on a written schedule. A verbal “done in a month” is not a plan. If you want a written schedule and a written price before any work starts, call Penhallow Remodeling North Miami at (888) 255-7411 for a free estimate. A real person answers, 24/7.

Written by the team at Penhallow Remodeling North Miami.

Getting started with Penhallow in North Miami

Every project starts with a conversation and a written price. Here is how to take the first step.

A project lead measuring a kitchen with the homeowner during a free estimate

Free on-site estimate

A project lead walks the job with you, measures it and hands you a written, line-item price. No obligation.

Book an estimate
A remodeling crew arriving at a home with lumber and tools

Your North Miami team

A local vetted partner works across North Miami and the towns around it, to the same written standard as every Penhallow job.

Areas we serve
A worker laying floor protection and a dust barrier before work starts

Read our written promise

What we promise on every job, written down, with the terms spelled out before any work starts.

Our promise
Need Construction help in North Miami? Licensed & insured · free written estimates
Call (888) 255-7411
Local Service Coverage

Request a Free Estimate in North Miami

Tell us what you need - Penhallow Remodeling North Miami responds fast. No obligation.